Work Profile Report [5W616]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 671/।।।(2)/16-46(एम.एल.ए.)/2015 टी0सी0, दिनांक 22.03.2016
TS Amount (lakhs) : 197.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
197.11
Resanction Cost :
197.11
Tentative Cost :
189.68
Saving
7.43
Exp. Upto Last Fy :
189.68
For CFY 2025-2026
Remaining :
7.43
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
189.68
Work completed
Sanction on : 9 years 1 month ago
22 Mar 2016
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
85 %
Tentative Completion date on : 5 years 1 month ago
31 Mar 2020
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 7.43 has been recorded as expected cost of work reduced from 197.11 to 189.68 . -- as on 06-May-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: