Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 3.3 | 3.300 | 0 | 0.000 | 0.000 |
5W619 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2062/।।।(2)/16-46(एम0एल0ए0)/2015 टी0सी0, दिनांक 30 जून 2016
TS Amount (lakhs) : 284.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
284.57
Resanction Cost :
284.57
Tentative Cost :
284.57
Exp. Upto Last Fy : 232.94
For CFY 2024-2025
Remaining : 51.63
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 232.94
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
8 years 2 weeks ago
30 Jun 2016
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा भुगतान शेष। -- as on 01-Apr-2023
Physical Peramenters