Administrative Approval Detail : शा0सं0 596/।।।(2)/19-46(एम0एल0ए0)/2017 टी.सी.-।, दिनांक 07.02.2019
TS Amount (lakhs) : 230.18 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
230.18
Resanction Cost :
245.29
Tentative Cost :
223.36
Saving
21.93
Exp. Upto Last Fy :
223.36
For CFY 2025-2026
Remaining :
21.93
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
223.36
In Maintenance After Completion
Sanction on : 6 years 3 months ago
07 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 5 months ago
16 Nov 2021
Actual Completion Date : 2 years 9 months ago
31 Jul 2022
Physical Linear Components
Remark
Overall Saving 21.93 has been recorded as expected cost of work reduced from 245.29 to 223.36 . -- as on 06-May-2025