Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
Closed Work 5W743 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: 30m Span steel girder motor bridge 72m Span motor Bridge near District Hospital 10m span motor bridge at Tunera baset
Administrative Approval Detail : शा0सं0 625/।।।(2)/19-47(एम0एल0ए0)/2017 टी.सी., दिनांक 11.02.2019
TS Amount (lakhs) : 110.42 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
110.42
Resanction Cost :
110.42
Tentative Cost :
110.42
Exp. Upto Last Fy : 108.08
For CFY 2024-2025
Remaining : 2.34
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 108.08
Work completed
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 95 %
Sanction on :
5 years 5 months ago
11 Feb 2019
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 year 3 weeks ago
20 Jun 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 10-Apr-2024