Work Profile Report [5W745]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 625/।।।(2)/19-47(एम0एल0ए0)/2017 टी.सी., दिनांक 11.02.2019
TS Amount (lakhs) : 117.13 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
117.13
Resanction Cost :
117.13
Tentative Cost :
117.13
Exp. Upto Last Fy :
96.35
For CFY 2025-2026
Remaining :
20.78
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
96.35
Work completed
Sanction on : 6 years 1 month ago
11 Feb 2019
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
100 %
Tentative Completion date on : 3 years 6 days ago
31 Mar 2022
Actual Completion Date : 3 years 6 days ago
31 Mar 2022
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 23-Dec-2024