Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.78 | 0.78 | 0.78 | 0 |
Closed Work 5W784 :
Administrative Approval Detail : शा0सं0-2238/।।।(2)/20-47(एम0एल0ए0)/2017, दिनांक 16.12.2020
TS Amount (lakhs) : 29.47 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.47
Resanction Cost :
29.47
Tentative Cost :
29.47
Exp. Upto Last Fy : 25.15
For CFY 2024-2025
Remaining : 4.32
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 25.15
Work completed
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 90 %
Sanction on :
3 years 7 months ago
16 Dec 2020
Tentative Completion date:
Yet To Decide
Actual Completion Date:
2 years 6 months ago
31 Dec 2021
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 31-Dec-2021
Physical Peramenters