Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
5W793 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-936/।।।(2)/21-46(एम.एल.ए.) /2017टी.सी.। दिनांक 30.03.2021
TS Amount (lakhs) : 97.1 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.10
Resanction Cost :
97.10
Tentative Cost :
97.10
Exp. Upto Last Fy : 80.87
For CFY 2024-2025
Remaining : 16.23
Demand : 5.00
Allotment : 3.00
Exp in CFY : 1.83
Total Up to Date Exp : 82.71
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
3 years 3 months ago
30 Mar 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 02-Jun-2023
Physical Peramenters