Work Profile Report [5W793]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-936/।।।(2)/21-46(एम.एल.ए.) /2017टी.सी.। दिनांक 30.03.2021
TS Amount (lakhs) : 97.1 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
97.10
Resanction Cost :
97.10
Tentative Cost :
97.10
Exp. Upto Last Fy :
85.96
For CFY 2025-2026
Remaining :
11.14
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
85.96
Work completed
Sanction on : 4 years 3 months ago
30 Mar 2021
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 1 month ago
24 May 2023
Actual Completion Date : 2 years 1 month ago
24 May 2023
Physical Linear Components
Remark
कार्य को वित्तीय एवं भौतिक रूप से पूर्ण कर लिया गया है। -- as on 12-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand