Work Profile Report [5W794]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-936/।।।(2)/21-46(एम.एल.ए.) /2017टी.सी.। दिनांक 30.03.2021
TS Amount (lakhs) : 68.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
68.44
Resanction Cost :
68.44
Tentative Cost :
68.44
Exp. Upto Last Fy :
29.81
For CFY 2024-2025
Remaining :
38.63
Demand :
5.00
Allotment :
0.00
Exp in CFY :
0.50
Total Up to Date Exp :
30.31
Work completed
Sanction on : 3 years 7 months ago
30 Mar 2021
Physical Progress:
At start of FY 2024-2025 :
85 %
Up to Date :
85 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 19-Sep-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand