Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
5W798 :
Work not linked with IM
Bridges on The Basis of AI: 30 m span Motor Bridge at Km7 of jakheda dakghat lamchula
Administrative Approval Detail : शा0सं0-1531/।।।(2)/21-47(एम0एल0ए0)/2017 टी0सी0-।।।, दिनांक 09.06.2021
TS Amount (lakhs) : 75.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
75.13
Resanction Cost :
75.13
Tentative Cost :
75.13
Exp. Upto Last Fy : 29.96
For CFY 2024-2025
Remaining : 45.17
Demand : 11.00
Allotment : 0.10
Exp in CFY : 0.04
Total Up to Date Exp : 30.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 1 month ago
09 Jun 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-Apr-2024
Physical Peramenters