Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
5W800 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1960(1)/।।।(2)/21-47(एम.एल.ए.)/2017टी.सी.।।
TS Amount (lakhs) : 75.95 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
75.95
Resanction Cost :
75.95
Tentative Cost :
75.95
Exp. Upto Last Fy : 67.69
For CFY 2024-2025
Remaining : 8.26
Demand : 8.26
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 67.69
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
3 years 2 weeks ago
02 Jul 2021
Tentative Completion date:
1 year 3 months ago
15 Apr 2023
Actual Completion Date:
1 year 3 months ago
15 Apr 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Oct-2023