Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
5W801 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1960(1)/।।।(2)/21-47(एम.एल.ए.)/2017टी.सी.।।
TS Amount (lakhs) : 92.58 Lacs
Financial Detail
Sanction Cost : 92.58 Lacs
Resanction Cost : 92.58 Lacs
Exp. Upto Last Fy : 59.58 Lacs
For CFY 2024-2025
Remaining : 33.00 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 59.58 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
2 years 10 months ago
02 Jul 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 30-Jun-2023
Physical Peramenters