Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
5W801 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1960(1)/।।।(2)/21-47(एम.एल.ए.)/2017टी.सी.।।
TS Amount (lakhs) : 92.58 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
92.58
Resanction Cost :
92.58
Tentative Cost :
92.58
Exp. Upto Last Fy : 59.58
For CFY 2024-2025
Remaining : 33.00
Demand : 10.00
Allotment : 5.00
Exp in CFY : 1.26
Total Up to Date Exp : 60.84
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
3 years 2 weeks ago
02 Jul 2021
Tentative Completion date:
1 month 2 weeks ago
28 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Jul-2024