Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
5W805 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2311(1)/।।।(2)/21-46(एम0एल0ए0)/2017, टी0सी0।।।, दिनांक 23.07.2021
TS Amount (lakhs) : 77.64 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
77.64
Resanction Cost :
77.64
Tentative Cost :
77.64
Exp. Upto Last Fy : 16.89
For CFY 2024-2025
Remaining : 60.75
Demand : 10.00
Allotment : 3.00
Exp in CFY : 1.00
Total Up to Date Exp : 17.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
2 years 11 months ago
23 Jul 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 19-Sep-2023