Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी, बागेश्वर का पत्रांक 525जि0यो0(1)/2021-22, दिनांक 05.07.2021
TS Amount (lakhs) : 45 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
45.00
Resanction Cost :
45.00
Tentative Cost :
45.00
Exp. Upto Last Fy :
32.26
For CFY 2025-2026
Remaining :
12.74
Demand :
0.00
Allotment :
0.03
Exp in CFY :
0.03
Total Up to Date Exp :
32.28
Work completed
Sanction on : 3 years 9 months ago
05 Jul 2021
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
95 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date : 1 year 3 weeks ago
13 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-Apr-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: 72m Span motor Bridge near District Hospital