Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16 | 16 | 16.000 | 0 | 0.000 | 0.000 |
5W838 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2 Road 3
Bridges on The Basis of AI: Kedar Bridge 36m Span motor bridge Dyangar 6.70m Span RCC bridge 24.50m Span motor bridge 10m span motor bridge 6m Span RCC motor bridge
Administrative Approval Detail : 1179/।।।(3)/2021-44(सी0आर0आई0एफ0)/2021, दिनांक 27.10.2021
TS Amount (lakhs) : 1545.18 Lacs
Financial Detail
Sanction Cost : 1,545.18 Lacs
Resanction Cost : 1,545.18 Lacs
Exp. Upto Last Fy : 1,544.61 Lacs
For CFY 2024-2025
Remaining : 0.57 Lacs
Demand : 0.53 Lacs
Allotment : 0.53 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1,544.61 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
2 years 6 months ago
27 Oct 2021
Tentative Completion date:
11 months 5 days ago
14 Jun 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 03-Oct-2023
Physical Peramenters