Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
5W853 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5661/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 17.11.2021
TS Amount (lakhs) : 98.74 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
98.74
Resanction Cost :
98.74
Tentative Cost :
98.74
Exp. Upto Last Fy : 39.22
For CFY 2024-2025
Remaining : 59.52
Demand : 40.00
Allotment : 30.00
Exp in CFY : 9.62
Total Up to Date Exp : 48.84
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 80 %
Sanction on :
2 years 8 months ago
17 Nov 2021
Tentative Completion date:
2 months 1 week from now
29 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 27-Jun-2024
Physical Peramenters