Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
5W853 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5661/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 17.11.2021
TS Amount (lakhs) : 98.74 Lacs
Financial Detail
Sanction Cost : 98.74 Lacs
Resanction Cost : 98.74 Lacs
Exp. Upto Last Fy : 39.22 Lacs
For CFY 2024-2025
Remaining : 59.52 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 39.22 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
2 years 6 months ago
17 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंगकोट एवं इन्टरकोट का कार्य पूर्ण। दीवार निर्माण एवं शेष कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters