Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.2 | 0 |
Closed Work 5W854 :
Administrative Approval Detail : 5661/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 17.11.2021
TS Amount (lakhs) : 85.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.36
Resanction Cost :
85.36
Tentative Cost :
85.36
Exp. Upto Last Fy : 76.17
For CFY 2024-2025
Remaining : 9.19
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 76.17
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 85 %
Sanction on :
2 years 8 months ago
17 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 year 3 weeks ago
20 Jun 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Oct-2023