Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.600 | 0.4 | 0.400 | 0.000 |
5W856 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5658(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 17.11.2021
TS Amount (lakhs) : 67.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
67.78
Resanction Cost :
67.78
Tentative Cost :
67.78
Exp. Upto Last Fy : 38.89
For CFY 2024-2025
Remaining : 28.89
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 38.89
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 85 %
Sanction on :
2 years 8 months ago
17 Nov 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
820मी0 पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters