Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.200 | 2.8 | 2.800 | 0.000 |
5W860 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6436(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 23.12.2021
TS Amount (lakhs) : 212.56 Lacs
Financial Detail
Sanction Cost : 212.56 Lacs
Resanction Cost : 212.56 Lacs
Exp. Upto Last Fy : 135.73 Lacs
For CFY 2024-2025
Remaining : 76.83 Lacs
Demand : 48.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 135.73 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
2 years 4 months ago
23 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
टापकोट स्तर ताक का कार्य पूर्ण। 0.20 किमी0 पी0सी0 कार्य पूर्ण। -- as on 02-Apr-2024
Physical Peramenters