Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.200 | 2.8 | 2.800 | 0.000 |
5W860 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6436(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 23.12.2021
TS Amount (lakhs) : 212.56 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
212.56
Resanction Cost :
212.56
Tentative Cost :
212.56
Exp. Upto Last Fy : 135.73
For CFY 2024-2025
Remaining : 76.83
Demand : 48.00
Allotment : 45.00
Exp in CFY : 40.33
Total Up to Date Exp : 176.05
Work completed
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
23 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Jul-2024
Physical Peramenters