Work Profile Report [5W860]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6436(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 23.12.2021
TS Amount (lakhs) : 212.56 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
212.56
Resanction Cost :
212.56
Tentative Cost :
184.56
Saving
28.00
Exp. Upto Last Fy :
135.73
For CFY 2024-2025
Remaining :
76.83
Demand :
48.35
Allotment :
48.35
Exp in CFY :
48.35
Total Up to Date Exp :
184.08
Work completed
Sanction on : 3 years 1 day ago
23 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 days ago
21 May 2024
Actual Completion Date : 7 months 3 days ago
21 May 2024
Physical Linear Components
Remark
Overall Saving 28 has been recorded as expected cost of work reduced from 212.56 to 184.56 . -- as on 23-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: