Work Profile Report [5W861]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 6440(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 23.12.2021
TS Amount (lakhs) : 107.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
107.85
Resanction Cost :
107.85
Tentative Cost :
97.38
Saving
10.47
Exp. Upto Last Fy :
89.26
For CFY 2024-2025
Remaining :
18.59
Demand :
8.12
Allotment :
8.12
Exp in CFY :
8.12
Total Up to Date Exp :
97.38
Work completed
Sanction on : 3 years 1 day ago
23 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
100 %
Tentative Completion date on : 1 year 7 months ago
08 May 2023
Actual Completion Date : 1 year 7 months ago
08 May 2023
Physical Linear Components
Remark
Overall Saving 10.47 has been recorded as expected cost of work reduced from 107.85 to 97.38 . -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: