Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
5W861 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6440(1)/।।।(2)/21-47(एम0एल0ए0)/2017टी0सी0, दिनांक 23.12.2021
TS Amount (lakhs) : 107.85 Lacs
Financial Detail
Sanction Cost : 107.85 Lacs
Resanction Cost : 107.85 Lacs
Exp. Upto Last Fy : 89.26 Lacs
For CFY 2024-2025
Remaining : 18.59 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 89.26 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
2 years 4 months ago
23 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Oct-2023
Physical Peramenters