Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.575 | 0.575 | 0.575 | 0 |
5W874 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : अर्थ एवं संख्याधिकारी, बागेश्वर के पत्रांक 525/जि0यो0(1)/2021-22, दिनांक 05.07.2021
TS Amount (lakhs) : 8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 8.00
Demand : 8.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
3 years 1 week ago
05 Jul 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 30-May-2023
Physical Peramenters