Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
5W892 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं सुख्याधिकारी, बागेश्वर का पत्रांक 552/जि0यो0/2022-23, दिनांक 08.09.2022
TS Amount (lakhs) : 10 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy : 2.40
For CFY 2024-2025
Remaining : 7.60
Demand : 7.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.40
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 10 months ago
08 Sep 2022
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters