Work Profile Report [5W892]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिला अर्थ एवं सुख्याधिकारी, बागेश्वर का पत्रांक 552/जि0यो0/2022-23, दिनांक 08.09.2022
TS Amount (lakhs) : 10 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
10.00
Resanction Cost :
10.00
Tentative Cost :
10.00
Exp. Upto Last Fy :
2.40
For CFY 2024-2025
Remaining :
7.60
Demand :
7.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.40
Construction Started
Sanction on : 2 years 3 months ago
08 Sep 2022
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
40 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 06-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: