Work Profile Report [5W901]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/111079/2023, ई फाईल संख्या-35078, दिनांक 29.03.2023
TS Amount (lakhs) : 224.62 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
224.62
Resanction Cost :
224.62
Tentative Cost :
224.62
Exp. Upto Last Fy :
125.38
For CFY 2024-2025
Remaining :
99.24
Demand :
51.19
Allotment :
50.00
Exp in CFY :
52.98
Total Up to Date Exp :
178.36
In Maintenance After Completion
Sanction on : 1 year 7 months ago
29 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
75 %
Up to Date :
100 %
Tentative Completion date on : 4 months 3 days ago
20 Jul 2024
Actual Completion Date : 5 months 4 weeks ago
26 May 2024
Physical Linear Components
Remark
पी0सी0 कार्य पूर्ण। -- as on 27-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: