Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.500 | 1.5 | 1.500 | 0.000 |
5W901 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/111079/2023, ई फाईल संख्या-35078, दिनांक 29.03.2023
TS Amount (lakhs) : 224.62 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
224.62
Resanction Cost :
224.62
Tentative Cost :
224.62
Exp. Upto Last Fy : 125.38
For CFY 2024-2025
Remaining : 99.24
Demand : 55.00
Allotment : 50.00
Exp in CFY : 2.82
Total Up to Date Exp : 128.20
Work completed
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 95 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
2 days 18 hours from now
20 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण। -- as on 27-Jun-2024
Physical Peramenters