Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
5W902 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/111079/2023, ई फाईल संख्या-35078, दिनांक 29.03.2023
TS Amount (lakhs) : 124.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
124.36
Resanction Cost :
124.36
Tentative Cost :
124.36
Exp. Upto Last Fy : 74.23
For CFY 2024-2025
Remaining : 50.13
Demand : 47.00
Allotment : 40.00
Exp in CFY : 0.19
Total Up to Date Exp : 74.42
Work completed
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
2 days 18 hours from now
20 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Jul-2024