Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.000 | 4 | 4.000 | 0.000 |
5W903 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/111076/2023, ई फाईल संख्या-48414, दिनांक 29.03.2023
TS Amount (lakhs) : 239.37 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
239.37
Resanction Cost :
239.37
Tentative Cost :
239.37
Exp. Upto Last Fy : 171.05
For CFY 2024-2025
Remaining : 68.32
Demand : 65.00
Allotment : 35.00
Exp in CFY : 27.75
Total Up to Date Exp : 198.79
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 85 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
2 months 3 weeks from now
10 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण। -- as on 22-Jun-2024
Physical Peramenters