Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 2.500 | 0.000 |
5W904 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/111076/2023, ई फाईल संख्या-48414, दिनांक 29.03.2023
TS Amount (lakhs) : 203.82 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
203.82
Resanction Cost :
203.82
Tentative Cost :
203.82
Exp. Upto Last Fy : 72.65
For CFY 2024-2025
Remaining : 131.17
Demand : 105.00
Allotment : 35.00
Exp in CFY : 30.23
Total Up to Date Exp : 102.88
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
3 months 2 days from now
20 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारों का निर्माण कार्य, 3.50 किमी0 सोलिंग कोट एवं 3.50 इन्टरकोट कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-Apr-2024
Physical Peramenters