Work Profile Report [5W905]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/111495/2023, ई फाईल संख्या-51770, दिनांक 31.03.2023
TS Amount (lakhs) : 316.25 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
330.60
Resanction Cost :
330.60
Tentative Cost :
330.60
Exp. Upto Last Fy :
153.12
For CFY 2024-2025
Remaining :
177.48
Demand :
123.00
Allotment :
125.00
Exp in CFY :
54.61
Total Up to Date Exp :
207.73
Construction Started
Sanction on : 1 year 7 months ago
31 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
75 %
Tentative Completion date on : 6 days 7 hours from now
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य प्रगति पर। -- as on 05-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand