Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
5W905 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/111495/2023, ई फाईल संख्या-51770, दिनांक 31.03.2023
TS Amount (lakhs) : 316.25 Lacs
Financial Detail
Sanction Cost : 330.60 Lacs
Resanction Cost : 330.60 Lacs
Exp. Upto Last Fy : 153.12 Lacs
For CFY 2024-2025
Remaining : 177.48 Lacs
Demand : 56.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 153.12 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 58 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
5 months 20 hours from now
20 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अतिरिक्त पहाड़ कटान एवं दीवार निर्माण का कार्य पूर्ण, 4.50 किमी0 सोलिंग, 4.00 किमी0 इन्टकोट, 1.5 किमी0 टापकोट का कार्य पूर्ण। स्कपर निर्माण एवं शेष कार्य प्रगति पर। -- as on 03-Apr-2024
Physical Peramenters