Work Profile Report [5W922]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 278.86 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
282.38
Resanction Cost :
282.38
Tentative Cost :
282.38
Exp. Upto Last Fy :
258.81
For CFY 2025-2026
Remaining :
23.57
Demand :
0.00
Allotment :
0.14
Exp in CFY :
0.14
Total Up to Date Exp :
258.95
Work completed
Sanction on : 2 years 4 months ago
18 May 2023
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
90 %
Tentative Completion date on : 1 year 2 days ago
30 Sep 2024
Actual Completion Date : 1 year 3 months ago
13 Jun 2024
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: