Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.82 | 6.82 | 3.500 | 3.32 | 3.320 | 0.000 |
5W925 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 127.72 Lacs
Financial Detail
Sanction Cost : 127.72 Lacs
Resanction Cost : 127.72 Lacs
Exp. Upto Last Fy : 59.89 Lacs
For CFY 2024-2025
Remaining : 67.83 Lacs
Demand : 49.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 59.89 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
1 year 1 day ago
18 May 2023
Tentative Completion date:
2 months 1 week from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार एवं स्कपर कार्य पूर्ण। 3.50 किमी0 में पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 13-Dec-2023
Physical Peramenters