Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.82 | 6.82 | 3.500 | 3.32 | 3.320 | 0.000 |
5W925 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 127.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
127.72
Resanction Cost :
127.72
Tentative Cost :
127.72
Exp. Upto Last Fy : 59.89
For CFY 2024-2025
Remaining : 67.83
Demand : 49.00
Allotment : 15.00
Exp in CFY : 0.00
Total Up to Date Exp : 59.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
1 month 6 days ago
11 Jun 2024
Actual Completion Date:
1 month 6 days ago
11 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 27-Jun-2024
Physical Peramenters