Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.79 | 14.79 | 4.000 | 10.79 | 6.790 | 0.000 |
5W926 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 275.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
281.17
Resanction Cost :
281.17
Tentative Cost :
281.17
Exp. Upto Last Fy : 128.72
For CFY 2024-2025
Remaining : 152.45
Demand : 115.00
Allotment : 83.47
Exp in CFY : 70.92
Total Up to Date Exp : 199.64
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 85 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
4 weeks 19 hours from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 कार्य पूर्ण। -- as on 22-May-2024
Physical Peramenters