Work Profile Report [5W927]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 307.76 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
307.76
Resanction Cost :
307.76
Tentative Cost :
307.76
Exp. Upto Last Fy :
61.85
For CFY 2024-2025
Remaining :
245.91
Demand :
240.00
Allotment :
160.00
Exp in CFY :
159.78
Total Up to Date Exp :
221.64
Construction Started
Sanction on : 1 year 6 months ago
18 May 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
80 %
Tentative Completion date on : 3 months 3 weeks ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 15-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand