Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 19 | 19 | 2.200 | 16.8 | 13.000 | 0.000 |
5W928 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 287.25 Lacs
Financial Detail
Sanction Cost : 294.80 Lacs
Resanction Cost : 294.80 Lacs
Exp. Upto Last Fy : 115.09 Lacs
For CFY 2024-2025
Remaining : 179.71 Lacs
Demand : 150.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 115.09 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 1 day ago
18 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.20 किमी0 पी0सी0 का कार्य पूर्ण। दीवारों एवं शेष कार्य प्रगति पर। -- as on 01-Apr-2024