Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9.2 | 9.2 | 0.000 | 9.2 | 7.000 | 0.000 |
5W929 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता0-पी0एम0जी0एस0वाई0-नि0।।।, दिनांक 18.05.2023
TS Amount (lakhs) : 153.03 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
153.03
Resanction Cost :
153.03
Tentative Cost :
153.03
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 153.03
Demand : 85.00
Allotment : 32.00
Exp in CFY : 31.39
Total Up to Date Exp : 31.39
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 48 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
1 month 1 week from now
31 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
6 किमी0 पी0सी0 कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters