Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.85 | 1.85 | 0.700 | 1.15 | 1.150 | 0.000 |
5W936 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/135768/2023, ई फाईल संख्या-35078, दिनांक 07.07.2023
TS Amount (lakhs) : 86.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
86.19
Resanction Cost :
86.19
Tentative Cost :
86.19
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 86.09
Demand : 60.00
Allotment : 40.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 60 %
Sanction on :
1 year 1 week ago
07 Jul 2023
Tentative Completion date:
1 month 3 weeks from now
13 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार एवं स्कपर कार्य प्रगति पर। -- as on 06-Mar-2024