Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
5W937 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/135768/2023, ई फाईल संख्या-35078, दिनांक 07.07.2023
TS Amount (lakhs) : 55.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.39
Resanction Cost :
55.39
Tentative Cost :
55.39
Exp. Upto Last Fy : 9.98
For CFY 2024-2025
Remaining : 45.41
Demand : 30.00
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 9.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
1 year 1 week ago
07 Jul 2023
Tentative Completion date:
1 week 4 hours ago
10 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 25-Jun-2024
Physical Peramenters