Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
5W946 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं सुख्याधिकारी, बागेश्वर का पत्रांक 716/जि0यो0(1)/2023-24, दिनांक 06.07.2023
TS Amount (lakhs) : 60 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.00
Resanction Cost :
60.00
Tentative Cost :
60.00
Exp. Upto Last Fy : 3.00
For CFY 2024-2025
Remaining : 57.00
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 3.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 95 %
Sanction on :
1 year 1 week ago
06 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 27-Mar-2024
Physical Peramenters