Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
5W971 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिला अर्थ एवं संख्याधिकारी, बागेश्वर का पत्रांक 716/जि0यो0(1)/2023-24, दिनांक 06.07.2023
TS Amount (lakhs) : 90 Lacs
Financial Detail
Sanction Cost : 90.00 Lacs
Resanction Cost : 90.00 Lacs
Exp. Upto Last Fy : 25.07 Lacs
For CFY 2024-2025
Remaining : 64.93 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 25.07 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
10 months 1 week ago
06 Jul 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारों का कार्य प्रगति पर। -- as on 01-Jan-2024
Physical Peramenters