Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.22 | 5.22 | 3.500 | 1.72 | 1.720 | 0.000 |
5W978 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/42543/2023 (ई पत्रावली संख्या-48456) दिनांक 31.07.2023
TS Amount (lakhs) : 105.56 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.56
Resanction Cost :
105.56
Tentative Cost :
105.56
Exp. Upto Last Fy : 90.78
For CFY 2024-2025
Remaining : 14.78
Demand : 14.00
Allotment : 14.00
Exp in CFY : 0.00
Total Up to Date Exp : 90.78
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 months 5 days ago
12 Apr 2024
Actual Completion Date:
3 months 5 days ago
12 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 07-Jun-2024
Physical Peramenters