Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.22 | 5.22 | 3.500 | 1.72 | 1.720 | 0.000 |
5W978 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/42543/2023 (ई पत्रावली संख्या-48456) दिनांक 31.07.2023
TS Amount (lakhs) : 105.56 Lacs
Financial Detail
Sanction Cost : 105.56 Lacs
Resanction Cost : 105.56 Lacs
Exp. Upto Last Fy : 90.78 Lacs
For CFY 2024-2025
Remaining : 14.78 Lacs
Demand : 14.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 90.78 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 month 1 week ago
12 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार एवं पक्की नाली का कार्य पूर्ण। 3.50 किमी0 पी0सी0 कार्य पूर्ण। काजवे, स्कपर एवं पैरापिट का कार्य पूर्ण। -- as on 06-Mar-2024
Physical Peramenters