Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
5W979 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/42543/2023 (ई पत्रावली संख्या-48456) दिनांक 31.07.2023
TS Amount (lakhs) : 10.6 Lacs
Financial Detail
Sanction Cost : 10.60 Lacs
Resanction Cost : 10.60 Lacs
Exp. Upto Last Fy : 4.55 Lacs
For CFY 2024-2025
Remaining : 6.05 Lacs
Demand : 4.05 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.55 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 month 1 week ago
08 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
नाली एवं रंग रोगन का कार्य पूर्ण। सुरक्षात्मक कार्य प्रगति पर। -- as on 01-Jan-2024
Physical Peramenters