Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
5W980 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/42543/2023 (ई पत्रावली संख्या-48456) दिनांक 31.07.2023
TS Amount (lakhs) : 27.61 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.61
Resanction Cost :
27.61
Tentative Cost :
27.61
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 27.61
Demand : 20.00
Allotment : 20.00
Exp in CFY : 18.32
Total Up to Date Exp : 18.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
4 months 2 days ago
15 Mar 2024
Actual Completion Date:
4 months 2 days ago
15 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 07-Jun-2024