Work Profile Report [5W987]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/144452/2023 ई फाईल संख्या-46395 दिनांक 07.08.2023
TS Amount (lakhs) : 223.3 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
223.30
Resanction Cost :
232.74
Tentative Cost :
200.30
Saving
32.44
Exp. Upto Last Fy :
137.00
For CFY 2025-2026
Remaining :
95.74
Demand :
40.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
137.00
Construction Started
Sanction on : 1 year 7 months ago
07 Aug 2023
Physical Progress:
At start of FY 2025-2026 :
20 %
Up to Date :
70 %
Tentative Completion date on : 1 month 1 week from now
15 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0-1, जी0-2, जी0-3 एवं 2.00 किमी0 पी0सी0 का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 02-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: Bhitarkot road Bridge
© PWD Uttarakhand