Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 2.000 | 0.000 |
5W987 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/144452/2023 ई फाईल संख्या-46395 दिनांक 07.08.2023
TS Amount (lakhs) : 223.3 Lacs
Financial Detail
Sanction Cost : 223.30 Lacs
Resanction Cost : 223.30 Lacs
Exp. Upto Last Fy : 47.90 Lacs
For CFY 2024-2025
Remaining : 175.40 Lacs
Demand : 122.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 47.90 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 months 1 week ago
07 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिफैक्ट कटिंग एवं दीवार निर्माण कार्य प्रगति पर। -- as on 23-Jan-2024
Physical Peramenters