Work Profile Report [5W988]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/144426/2023 ई फाईल संख्या-50154, दिनांक 07.08.2023।
TS Amount (lakhs) : 133.65 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
133.65
Resanction Cost :
133.65
Tentative Cost :
118.65
Saving
15.00
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
133.55
Demand :
1.00
Allotment :
0.03
Exp in CFY :
0.03
Total Up to Date Exp :
0.13
Construction Started
Sanction on : 1 year 4 months ago
07 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
2 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 15 has been recorded as expected cost of work reduced from 133.65 to 118.65 . -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: