Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.000 | 0.5 | 0.500 | 0.000 |
5W990 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-।/54061/2023 ई-फाईल संख्या-48456, दिनांक 14.09.2023
TS Amount (lakhs) : 111.33 Lacs
Financial Detail
Sanction Cost : 111.33 Lacs
Resanction Cost : 111.33 Lacs
Exp. Upto Last Fy : 69.92 Lacs
For CFY 2024-2025
Remaining : 41.41 Lacs
Demand : 21.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 69.92 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
8 months 5 days ago
14 Sep 2023
Tentative Completion date:
2 months 2 days ago
17 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
4.00 किमी0 पी0सी0 कार्य पूर्ण। दीवार निर्माण कार्य पूर्ण। स्कपर एवं पैरापिट निर्माण कार्य पूर्ण। -- as on 06-Mar-2024
Physical Peramenters