Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.5 | 5.5 | 3.400 | 2.1 | 2.100 | 0.000 |
5W991 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-।/54061/2023 ई-फाईल संख्या-48456, दिनांक 14.09.2023
TS Amount (lakhs) : 104.69 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
104.69
Resanction Cost :
104.69
Tentative Cost :
104.69
Exp. Upto Last Fy : 78.40
For CFY 2024-2025
Remaining : 26.29
Demand : 26.29
Allotment : 26.29
Exp in CFY : 0.00
Total Up to Date Exp : 78.40
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
10 months 3 days ago
14 Sep 2023
Tentative Completion date:
4 months 3 days ago
14 Mar 2024
Actual Completion Date:
4 months 3 days ago
14 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 22-May-2024
Physical Peramenters