Work Profile Report [5W995]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0-।/164719/2023, फाईल संख्या-57670, दिनांक 27.10.2023
TS Amount (lakhs) : 230.61 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
230.61
Resanction Cost :
230.61
Tentative Cost :
230.61
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
230.61
Demand :
121.25
Allotment :
35.00
Exp in CFY :
106.25
Total Up to Date Exp :
106.25
Construction Started
Sanction on : 1 year 3 weeks ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
70 %
Tentative Completion date on : 5 months 1 week from now
06 May 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दीवार निर्माण, कच्ची एवं पक्की नाली निर्माण, पैरापिट निर्माण् कार्य पूर्ण। बी0सी0 का कार्य प्रगति पर। -- as on 26-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: