Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.675 | 2.675 | 0.000 | 2.675 | 1.670 | 0.000 |
5W995 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-।/164719/2023, फाईल संख्या-57670, दिनांक 27.10.2023
TS Amount (lakhs) : 230.61 Lacs
Financial Detail
Sanction Cost : 230.61 Lacs
Resanction Cost : 230.61 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 230.61 Lacs
Demand : 50.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
6 months 3 weeks ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवारों का निर्माण कार्य पूर्ण। काॅजवे की मरम्मत का कार्य प्रगति पर। -- as on 27-Mar-2024
Physical Peramenters