Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 42 | 42 | 42 | 0 |
5W996 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-4088/।।।(2)/2023-(प्रा0आ0)/2023, दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
535.38
Resanction Cost :
535.38
Tentative Cost :
535.38
Exp. Upto Last Fy : 67.01
For CFY 2024-2025
Remaining : 468.37
Demand : 464.00
Allotment : 250.00
Exp in CFY : 210.64
Total Up to Date Exp : 277.66
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 50 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Apr-2024
Physical Peramenters