Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 101.5 | 101.5 | 101.5 | 0 |
5W997 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-4088/।।।(2)/2023-(प्रा0आ0)/2023, दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
253.84
Resanction Cost :
253.84
Tentative Cost :
253.84
Exp. Upto Last Fy : 39.78
For CFY 2024-2025
Remaining : 214.06
Demand : 200.00
Allotment : 100.00
Exp in CFY : 26.68
Total Up to Date Exp : 66.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 25 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 29-Feb-2024
Physical Peramenters