Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 60.42 | 60.42 | 60.42 | 0 |
5W998 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-4088/।।।(2)/2023-(प्रा0आ0)/2023, दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
287.27
Resanction Cost :
287.27
Tentative Cost :
287.27
Exp. Upto Last Fy : 6.90
For CFY 2024-2025
Remaining : 280.37
Demand : 250.00
Allotment : 130.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.90
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 29-Feb-2024
Physical Peramenters