Work Profile Report [5W998]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शा0सं0-4088/।।।(2)/2023-(प्रा0आ0)/2023, दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
287.27
Resanction Cost :
287.27
Tentative Cost :
287.27
Exp. Upto Last Fy :
6.90
For CFY 2024-2025
Remaining :
280.37
Demand :
250.00
Allotment :
113.00
Exp in CFY :
176.13
Total Up to Date Exp :
183.04
Construction Started
Sanction on : 1 year 3 weeks ago
01 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3818मी0 क्रैश बैरियर का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 08-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand