Work Profile Report [60W19]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/Annual Plan/2022-23/Dehradun/09
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
499.38
Resanction Cost :
499.38
Tentative Cost :
499.38
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
499.38
Demand :
0.00
Allotment :
273.38
Exp in CFY :
273.38
Total Up to Date Exp :
273.38
Construction Started
Sanction on : 1 year 9 months ago
02 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
90 %
Tentative Completion date on : 3 months 2 weeks ago
07 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work in progress. -- as on 10-Nov-2023
Assets :