Administrative Approval Detail : NH-28014/01/2014/UR/CRF/NH-2(Zone-1) dated 06-03-2019 (Job No. CRF-UR-2021-22-29 to 36) Uttarakhand Govt. Go 1311/III(3)/2020-28(CRF)/19 dt. 23.10.2020
TS Amount (lakhs) : 3332.41 Lacs
Budget Financial Head : CRIF ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3332.41
Resanction Cost :
3332.41
Tentative Cost :
3332.41
Exp. Upto Last Fy :
2,513.01
For CFY 2024-2025
Remaining :
819.40
Demand :
20.00
Allotment :
66.63
Exp in CFY :
66.63
Total Up to Date Exp :
2,579.63
Work completed
Sanction on : 5 years 9 months ago
06 Mar 2019
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 4 months ago
31 Jul 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work Completed. -- as on 14-Dec-2023
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: RCC Box cell 60 M