Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 27 | 27 | 27 | 0 |
60W8 :
Administrative Approval Detail : RO/UK/ANNUAL PLAN/2020-21/DEHRADUN/03 dated 26.03.2021 Job No. NH- 72(New No-07)-UR- 2021-22- 592 dated 26-03-2021
TS Amount (lakhs) : 2807.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2807.41
Resanction Cost :
2807.41
Tentative Cost :
2807.41
Exp. Upto Last Fy : 516.28
For CFY 2024-2025
Remaining : 2,291.13
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 516.28
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
26 Mar 2021
Tentative Completion date:
1 year 10 months ago
30 Aug 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work Completed. -- as on 20-May-2023
Physical Peramenters